Project
Start: Upon receipt of full funding
Application/Service
Technical and Creative Design: 2.5 months
>email
processor design — 2 weeks; > semantic inference engine
design — 2 weeks; > web service, media database design
- 2 weeks; > admin service design — 1 week; > graphic
design concept development — 3 weeks.
Application/Service
Production — 3 Months
>
email processor development — 3 months; > illustration
and visualization production — 1.5 month; > web interface
design — 1.5 month; > web interface development —
1.5 months.
Beta
Testing — 1 Month
>
pre-launch testing with limited set of users, design and technology
iteration — 1 month.
Public Project Launch — 6 Months after start date
project
budget >
|